| Fabric Apholstered Wall Coverings |
SECTION 09950 |
| 1. |
General |
|
| 1.1 |
Related Work in Other Sections |
|
|
.1 |
Concrete Walls |
Section |
|
.2 |
Mastonry Walls |
Section |
|
.3 |
Finish Carpentry or Millwork |
Section |
|
.4 |
Gypsum Wallboard |
Section |
|
.5 |
Electrical Outlets |
Section |
| 1.2 |
Guarantee |
|
|
.1 |
Provide a two year written
guarantee against defects in material, workmanship and/or fabric
sagging. |
| 1.3 |
Work Specified |
|
|
.1 |
Fabric Wall Panels designated
as FWP on drawings or Room Finish Schedule. |
| 1.4 |
Fire Rating |
|
|
.1 |
Flame spread
rating of each component of the assembly not to exceed 25
as to CAN/ULC-S102-M88 and ASTM E-84 testing. |
| 1.5 |
Samples |
|
|
.1 |
Submit 300mm x 300mm samples
for final approval prior to ordering. Label samples with manufacturer's
name, quality, color, texture and weight. |
| 1.6 |
Delivery / Storage / Handling |
|
|
.1 |
Deliver materials and
assemblies to site when areas of application are erected and
ready to receive application. |
|
.2 |
Store all material flat
in a clean, dry storage area. Do not store material on end
or in an upright position. |
| 2. |
Products |
|
| 2.1 |
Framework |
|
|
.1 |
12.5mm thick fire retardant
PVC extrusion to profile specified or detailed on drawings. |
| 2.2 |
Backing |
|
|
.1 |
(See Technical
Data for selection of appropriate backing or core material.) |
| 2.3 |
Fabric |
|
|
.1 |
(Specify fabric
as per manufacturers specifications. Specify additional
fabric if required for owners maintenance.) |
| 3. |
Execution |
|
| 3.1 |
Installation |
|
|
.1 |
Fasten PVC track securely
to wall surface in continuous strips around perimeter of wall or
to panel sizes indicated on drawings. Fastenings to be as
recommended by the manufacturer and approved by the Architect /
Designer. |
|
.2 |
Ensure PVC track is aligned
horizontally and vertically and that mitred and butt joints are
square and flush. |
|
.3 |
Install backing material
neatly within the perimeter of the PVC framework. Use full sheets
and ensure that butt joints are flush and do not telegraph through
fabric face. Backing to be fastened or adhered to wall surface
as required. |
|
.4 |
Install PVC shims around
outlet boxes, receptacles, etc., which occur in the fabric area.
Install securely and ensure that all cover plates, etc., mount flush
on fabric surface. |
|
.5 |
Fabric to be cut by thread
or pattern, whichever is applicable. Fabric to have sewn flat
seams or abutted panels as detailed. |
|
.6 |
Stretch fabric
over PVC framework and insert into the jaw of the extrusion using
appropriate tools. Fabric to be squared and even, concealing
the PVC extrusion. After fabric is stretched over framework, trim
all edges and insert remaining salvage material fully into jaws
of the PVC extrusion. |
| 3.2 |
Clean-up |
|
|
.1 |
Clean fabric surfaces
of dust, dirt or other contaminants. |
|
.2 |
Remove debris
and leave areas neat and clean. |
|
|
|